In project management, a change order is a component of the change management process whereby changes in the Scope of Work agreed to by the owner and other team members are implemented.
A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original data.
Change orders are common to most projects, and very common with large projects. After the original scope is formed, a team member may decide that the original plans do not best represent the definition for the finished project. Accordingly, the team member(s) will suggest an alternate approach.
Common causes for change orders to be created are:
- The project's work was incorrectly estimated
- The customer or project team discovers obstacles or possible efficiencies that require them to deviate from the original plan
- The customer or project team are inefficient or incapable of completing their required deliverables within budget, and additional money, time, or resources must be added to the project
- During the course of the project, additional features or options are perceived and requested.
- The contractor looks for work items to add to the original scope of work at a later time in order to achieve the lowest possible base bid price, but then add work items and fee back on once the contractor has been hired for the work. This is an exploitative practice.
A project manager then typically generates a change order that describes the new work to be done (or not done in some cases), and the price to be paid for this new work. Once this change order is submitted and approved it generally serves to alter the original contract such that the change order now becomes part of the contract.